HRERA registration lapsedReg 389 OF 2017 DATED 22.12.2017 Lapsed ProjectValid to 31/12/2020
Illustrative image1 / 1
Under ConstructionBuyRegistration lapsedOngoing project

Fernhill (phase-2)

Ansal Properties & InfrastructureGurugram, Sector 91

Price on request

HRERA filings carry no unit pricing — we confirm the current band with the developer.

RERA registered — RERA-GRG-718-2020, valid to 31/12/2020

Land area
9.912 acres
Declared completion
Dec 2019
Built
70%
Project cost
₹249.80 Cr

Configurations

REP-I Part C
  • Tower-E,F (2bhk+2t+Kids)
  • Tower-E,F (2bhk+2t)
  • Tower-G,H,J,K,L&M(3bhk+3t)
  • Tower-G,H,J,K,L&M(2bhk+2t+Kids)

Delivery status

REP-I Part C
Infrastructure
70%
Declared completion
Dec 2019
Status
Overdue
Layout approved
20-05-2014
Building plan
20-05-2014

The completion date the promoter filed has already passed, with infrastructure reported 70% complete. Treat the handover date as unmet until a fresh quarterly progress report says otherwise.

Approvals & compliance

REP-I Part E

Statutory approvals: 8 obtained, 2 pending

Roads
GMDA · not taken
Water Supply
GMDA · not taken
Electricity
DHBVN · not taken
Sewage Disposal
GMDA · not taken
Storm Water Drainage
GMMDA · not taken

Agency sign-off for external connections stands at 0 of 5 obtained. Internal approvals and external connections are separate gates — worth raising both before you book.

Licence & legal

REP-I Part B
RERA registration
389 OF 2017 DATED 22.12.2017 Lapsed Project
Valid up to
31/12/2020
Promoter is licensee
No
Promoter CIN
L45101DL1967PLC004759
Permissible FAR
175%
Proposed FAR
175%

About this project

Fernhill (phase-2) is a group housing project by M/s. Ansal Properties & Infrastructure Ltd. in Sector 91, Gurugram, registered with the Haryana Real Estate Regulatory Authority under 389 OF 2017 DATED 22.12.2017 Lapsed Project. The promoter has declared a project area of 9.912 acres. 8 statutory approvals are recorded as obtained and 2 as still pending. Agency sign-off for external services stands at 0 of 5 — covering roads, water, electricity, sewage and storm-water drainage. The completion date filed with the authority was Dec 2019, with infrastructure reported 70% complete — that date has now passed. Ltd.. All figures are as declared by the promoter to HRERA Gurugram and are not independently verified.

Rest of the filing

REP-I
Registration number
RERA-GRG-718-2020
Register status
Marked lapsed in the HRERA register

Location

REP-I Part A

Gurugram, Sector 91

Open in Google Maps

Every figure on this page is as declared by the promoter to HRERA Gurugram — Form REP-I and is not independently verified by us. Registration status and availability can change between filings. View the source filing.

Related Properties

More registered projects nearby and of the same kind, from the HRERA Gurugram register.

Find Your Perfect Space in Manesar & Gurgaon

Tell us the size, budget and area you need. We shortlist, arrange visits and check the papers before you sign.

Call +91 97187 77555