Tathastu II
Price on request
HRERA filings carry no unit pricing — we confirm the current band with the developer.
RERA registered — RERA-GRG-1269-2023, valid to 14/11/2027
- Land area
- 8.975 acres
- Declared completion
- Oct 2027
- Project cost
- ₹361.45 Cr
Delivery status
REP-I Part C- Declared completion
- Oct 2027
- Status
- On schedule
- Layout approved
- 23-01-2023
- Building plan
- 23-01-2023
Approvals & compliance
REP-I Part EStatutory approvals: 1 obtained, 0 pending
- Roads
- NA · not taken
- Water Supply
- HSVP DIVISION VI (ASSURANCE TAKEN) · approved
- Electricity
- DHBVN (ASSURANCE TAKEN) · approved
- Sewage Disposal
- HSVP DIVISION VI (ASSURANCE TAKEN) · approved
- Storm Water Drainage
- NA · not taken
Agency sign-off for external connections stands at 3 of 5 obtained. Internal approvals and external connections are separate gates — worth raising both before you book.
Amenities
REP-I Part C- Club House/Community Centre
- Electricity Supply System
- Internal Roads and Pavements
- Playgrounds and Parks
- Renewable Energy System
- Security and Fire Fighting
- Sewage Treatment & Garbage Disposal
- Shopping Area
- Storm Water Drainage
- Street Lighting
- Water Supply System
These are the facilities the promoter costed into its service plan estimates — not a marketing list.
Licence & legal
REP-I Part B- RERA registration
- GGM/677/409/2023/21 DATED 30.01.2023
- Valid up to
- 14/11/2027
- Town planning licence
- 188 of 2022
- Promoter is licensee
- Yes
- Promoter CIN
- U45200DL2011PTC212556
- Permissible FAR
- 240%
- Proposed FAR
- 240%
- Litigation declared
- No
About this project
Tathastu II is a group housing project by Desi Construction Private Limited in Sector 5, Sohna, registered with the Haryana Real Estate Regulatory Authority under GGM/677/409/2023/21 DATED 30.01.2023. The promoter has declared a project area of 8.975 acres. All 1 statutory approvals listed in the filing are recorded as obtained. Agency sign-off for external services stands at 3 of 5 — covering roads, water, electricity, sewage and storm-water drainage. The filed completion date is Oct 2027. It is developed on town-planning licence 188 of 2022. All figures are as declared by the promoter to HRERA Gurugram and are not independently verified.
Rest of the filing
REP-I- Registration number
- RERA-GRG-1269-2023
Location
REP-I Part ASohna, Sector 5
Open in Google MapsEvery figure on this page is as declared by the promoter to HRERA Gurugram — Form REP-I and is not independently verified by us. Registration status and availability can change between filings. View the source filing.
Related Properties
More registered projects nearby and of the same kind, from the HRERA Gurugram register.


Central Park Flower Valley
Price on request
Sector 32, Sohna · by St Patricks Realty

Central Park Flower Valley - Phase I
Price on request
Sector 29, Sohna · by St Patricks Realty